The site is in the final weeks of construction prior to practical completion in early October. Internal work is in full swing with flooring and joinery being installed. The majority of bedrooms are now complete. Work has commenced on the foyer and reception area. The external works associated with the laneways and footpaths has commenced. The Big Dig Archaeology Education centre is progressing well. Many of the interpretation elements are now in production and are expected to be installed on the site in October.

Bookings are now opne on www.yha.com.au from 1st December onwards. Please note that December 30th and 31st are fully booked! Bookings for dates earlier than December will be opened in coming weeks.